Båsum Drilling has completed drilling of 91 wells in the energy well park to Arcus on Gjellerårsen. It went by about 7000 meters of insulated gls track pipes from wells down to 300 m depth, and in the technical room.
Figures: There are drilled 27,300 gls track meters which corresponds to a power output of the heat of approx. 900 kw, while this may geothermal gls track energy used for cooling of the building that is going to be a very reasonable additional effect.
Energy Well Park is special in that it is built in prism shape. The wells have a distance of 2.1 meters apart and a distance of 5 meters on top of each other beyond. gls track According to researchers, this form of well park provide a better utilization of the storage effect in the mountains.
Advisers recommendation gls track Norconsult came in its advisory report that there were two options for energy Arcus facility at Gjellerårsen outside Oslo, whether the purchase of district heating from Akershus Energi, with a minimum investment of just under 10 million dollars, provided that the cost of performance gls track of district including heat exchangers gls track is was covered by Akershus energy.
The other option was the construction of a dedicated power plant, which was estimated to cost 38 million. For this option was included LPG gas boilers totaling gls track 5.5 MW electric boiler (1.2 MW) and heat pump of 2.2 MW. It's added up to about 20,000 m wells. Each well will be approx. 200 m deep.
Costs include collector gls track filled with liquor and supply lines and pump. It is understood that the use of industrial heat pump / cooling machine of high quality with ammonia as a refrigerant. This has higher efficiency than standard units and can deliver heat up to 68 C. There is provided a power plant of 360 m in this case.
The most probable scenario with the increase in energy prices shows that the heat pump option is better than the alternative of heating, concluded Norconsult, and thus got Båsum AS the contract drilling of wells for its own energy center, and thus lower operating costs for the next fifteen to twenty years. With its own energy center Arcus would have full control on their annual costs, and not be subjected to varying flow rates from an external supplier.
Environmental good options Both options are comparable environmental, Norconsult writes in his report Fjernvarme option will be more expensive in operation gls track at generally higher energy prices than today. It must not be accepted higher price than the Akershus energy have suggested. If the developer wants to tie the minimum capital and reduce investment risk as well as resources for the operation of the plant through the outsourcing of energy supply, district heating recommended option. If the developer wants security gls track against rising energy prices and increased energy consumption for heating and cooling in the future, recommended heat pump option, and the latter solution was thus chosen.
Going for swelled gls track Read more ...
- 100 wells to the new Østfold Hospital - Are mandatory connection must be removed - Energy wells a safe investment - Thermal response test pays - Energy wells shut outside air as an energy - Geothermal energy on the rise - There are still differences in heat pumps Foundation